Since Sept. 13, flaggers have been running alternating one-way traffic on US 6 east of Fruita. Crews work from 7 p.m. to 7 a.m., Sunday night through Friday morning, on a $3 million resurfacing job between mile points 20 and 26. That's the US 6 project you can see. It's scheduled to wrap up in November and leave a smoother road with fresh striping.
A second, larger US 6 project exists so far only as maps, slides and a planning calendar. The Colorado Department of Transportation wants to widen US 6 from South Pine Street in Fruita to 22 Road in Grand Junction and put a raised median down much of the corridor. That would end some left turns into and out of the homes, businesses and side roads along the highway. No construction money is secured and there's no start date. The access rules that would govern the finished road are being written right now anyway.
Two projects, one stretch of highway
The two efforts overlap on the map and run on very different clocks.
| Resurfacing | Widening and access plan amendment | |
|---|---|---|
| Where | US 6, MP 20 to MP 26, east of Fruita | 18 Road/South Pine Street to 22 Road |
| What | Two-inch mill-and-fill, guardrail repairs, delineators, striping, minor ADA updates | Two lanes to four with a raised median, U-turns, Continuous Green-T intersections |
| Cost | $3 million | $21.9 million east of 20 Road and $41.5 million west of it, both regional plan estimates |
| Status | Scheduled September to November 2026 | Early design, construction unfunded, no timeline |
The resurfacing is maintenance. CDOT's project page still lists the September-to-November window and sends drivers to COtrip.org for real-time conditions while crews finish.
The widening comes in two phases. On CDOT's US 6 West Access Control Plan page, Phase One is the segment east of 20 Road and Phase Two is the segment west of 20 Road, the side closer to Fruita.
The rulebook came first, in 2010
The access plan predates the widening by years. In 2010, CDOT, the City of Fruita, the City of Grand Junction and Mesa County adopted a US Highway 6 Access Control Plan covering the highway from Loma to Grand Junction. CDOT's page describes an access control plan as a way for local governments and the state to plan future access to a state highway together, so access isn't set purely by the State Highway Access Code.
So the widening itself doesn't decide whether a given driveway keeps its left turn. The amended access plan decides that, and the agencies now say the 2010 plan has to change to support widening between 18 Road and 22 Road. CDOT says the team is weighing business and residential access concepts for right-of-way impact, parking, access control, intersection configuration and overall traffic effects.
What a raised median does to a left turn
CDOT design engineer Matt Casey and traffic safety engineer Mark Bunnell brought the concept to Fruita City Council on Sept. 29. According to the council minutes, the plan widens US 6 from two lanes to four with a raised median. Some intersections would get U-turns and others Continuous Green-T designs "to channel left turns and allow eastbound traffic to continue to flow." TV coverage called the larger county-road intersections Florida-T intersections, and described the road as a "two-lane, two-way corridor," meaning two lanes in each direction.
The basic driveway concept CDOT showed was right-in, right-out access with dedicated U-turns. Today, someone leaving a property on the south side of US 6 to head west can turn left across traffic. Under that concept they'd turn right, go to a dedicated U-turn and come back. The slides also covered shared driveways, access for corner properties from side streets, cutting a property down to one access point, and three-quarter movement accesses.
The case CDOT made to council was about crashes. One slide said 3 out of 4 driveway crashes involve left turns, and another said U-turns are safer than direct left turns from driveways. Those slides describe driveways in general, not crash counts from this stretch of US 6.
At the October open houses, KJCT reported, CDOT project manager Hannah McCutcheon put it this way: "With safety being our biggest goal with some of these changes, I guess the more major ones is eliminating those left out access points." She pointed to the grid of county roads off the highway as the way drivers would adjust, saying "you just have to be able to plan ahead to learn, maybe a new route to get to where you're trying to go." KKCO 11 News ran the same account.
The calendar is moving faster than the money
"No funding, no timeline" refers to construction. The access plan amendment has its own schedule, and CDOT laid it out for Fruita council:
- September 2026: presentations to local agencies
- October 2026: updated access control plan open house
- November 2026: one-on-one meetings with property owners
- January 2027: updated intergovernmental agreement
The first two steps are done. CDOT held open houses Oct. 21 at its Bookcliff Conference Room, 2328 G Road in Grand Junction, and Oct. 22 at the Fruita Civic Center, 325 E. Aspen Ave. The City of Fruita's Oct. 23 weekly update confirmed the Civic Center session. It didn't announce any formal city position. Back in September, council members had asked CDOT about holding an extra open house for Fruita residents, property owners and business owners, "due to how engaged the Fruita community typically is."
So November is when CDOT plans to sit down with owners along the corridor, and an updated agreement among the four agencies is due early next year. All of that comes ahead of any construction contract.
The money is the slow part. The adopted 2050 Grand Valley Regional Transportation Plan, posted on Mesa County's regional transportation planning page, lists the 20 Road to 22 Road segment as a Tier 1 project for 2025 to 2029 at an estimated $21.9 million. The 18 Road to 20 Road segment, nearest Fruita, is Tier 1 for 2030 to 2039 at $41.5 million. Tier 1 is based on projected federal, state and local revenue, which is why CDOT can still say in October 2026 that construction funding isn't secured. The segment west of 20 Road also costs nearly twice as much as the eastern one and sits a decade later on the regional list.
What isn't public yet
CDOT hasn't published a road-by-road list showing which intersections between Pine Street and 22 Road get a Green-T, a U-turn, a closure or full access. The exhibits use a legend of closures, right-in/right-out, three-quarter access, full-movement access and alternate access. The study page doesn't give a comment deadline either. The council minutes note that CDOT "will still need to go through more analysis."
For now, the detailed answer for any one driveway sits in the project exhibits and in conversation with the project team. CDOT's comment page takes public input and lists contact information for questions.
This post is general information, not legal advice. If you own property along the corridor, confirm how a proposed access change affects your parcel with CDOT and your own attorney.
If you own a home or land along US 6 and want to know how the access plan could play into a future sale or purchase, call or text Josh McGuire for a quick market consult. Josh follows the corridor and can talk through what buyers are asking about.